Council engages in a comprehensive program of maintenance and upgrades of our facilities and Infrastructure. Stay up to date with the latest works and any road closures or other impacts on amenity.

CBD Footpath Renewal Program - Fairy Street (Koroit to Timor streets)
Works: The renewal of this section of Fairy Street footpath will take place on the west side of Fairy Street between Koroit and Timor streets.
Duration: Two weeks from Friday, November 22.
Impact: Footpath fencing and pedestrian detours in place. Minor traffic delays may be experienced to allow trucks to access the site. Access to businesses will be available for the majority of the work.
Contact: Project Manager Adam Bain, 0437 857 574 

Pecten Avenue Reserve (12-16 Pecten Avenue, Warrnambool)
Works: Construction of the West Warrnambool Neighbourhood House.
Duration: Up to 12 weeks.
Impact: The works area will be divided off via temporary fencing with the remainder of the reserve available for public use. Pedestrians within the reserve are advised to observe all signage and delineation items.
Contact: Karen Hardess, Project Manager on (03) 5559 4800.

2024 Road Resealing Program
Works: 
Road resealing.
Duration: November 25-30. Resealing work at each location will usually be completed in one day.
Impact: Sections of road may will be under traffic control, which brief full closures also in place. Please overserve all signage.
Locations: 
Wangoom Road: House No. 35 to Aberline Rd
Balmoral Road: Toal Dr to Jason St
Tulsa Close: to Moonah St to End
Moore Street: Kiama Ave to Tozer Rd
Morriss Road: Examiner Cres to Vickers Dr
Hider Street: Princes Hwy to Panorama Ave
Hopetoun Road: Wayamba Ct to Chishlom St
Murray Street: Lava St to Kerr St
Kerr Street: Hider St to Hyland St
Fitzroy Road: Raglan Pde to Laverock Grove
Fitzroy Road: Laverock Grove to Giffen Street
Simpson Street: Princes Hwy to Jukes St
Gladstone Street: Marfell Rd to Otway Rd
Harris Street: Wellington St to Merri River Bridge
Hopkins Pt Road: Hopkins Bridge to Darlymp Dr
Ward Street: Nicholson St to Merri St

Taits Road
Works: Footpath construction
Commencement Date: Week commencing Monday 4 November 2024
Duration: 4 Weeks
Impact: Motorists and Pedestrians are advised to observe all signage.
Contact: Project Manager, Darron Pascoe, 0419 976 988.

Viaduct Road
Works: Road revetment.
Duration: Week commencing Monday 11 November 2024 for 4 weeks.
Impact: Motorists and pedestrians are advised to observe all signage.
Contact: Don Allen, Construction Engineer on 0419 389 638.

Ziegler Parade (38 – 62 Ziegler Parade, Allansford)
Works: Road upgrade including parking and drainage improvements.
Duration: Week commencing Monday 18 November 2024 for 14 weeks.
Impact: Motorists and pedestrians are advised to observe all signage.
Contact: Don Allen, Construction Engineer on 0419 389 638.

Vegetation Clearing in Vicinity of Power Line Conductors
Under the Code of Practice for Electric Line Clearance Council must maintain vegetation clearance around power lines in compliance with the Electricity Safety (Electric Line Clearance) Regulations 2020. Council is hereby giving notice that trimming of vegetation on public land within the declared area of the City will be conducted over the next 60 days (from August 10, 2024) in order to maintain the required clearance space around power lines prescribed by the Code. For further information contact Council’s Tree Management Unit on 5559 4800 or email contact@warrnambool.vic.gov.au